Residual Risk vs Secondary Risk

--此處輸入引言--


--以下是內文--
No. 110 on page 56 of Crosswind (厚):
The team implemnted a risk response plan when a vendor was unable to fulfill a contract commitment. The response was to choose another vendor. However, in this industry, it's hard to find a good company, and the one selected isn't that much better. The new company is somewhat better at meeting the terms of the contract, but still has some issue from time to time. What best describes these issues?
(A) Secondary risk
(B) Workaround
(C) Residual risk
(D) Risk respose plan
The answer of Crosswind (厚) is (C)
Why not (A) Secondary risk?

The definition of secondary risk means that risks result from the execution of a risk response. Right?  Can someone clarify this?
 

(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

A trigger is an indicator that a risk even will or could occur

--此處輸入引言--


--以下是內文--
183. All of the following are correct regarding risk triggers except...
(A) A trigger does not mean a risk will occur
(B) A trigger come before a risk
(C) A trigger in an indicator that a risk event could occur
(D) A trigger is an indicator that a risk even will occur 
The answer of Crosswind (厚) is (D)
I don't think that it's correct answer.
Refer to No. 26 of Crosswind (薄) on page 111, the anwser is  A trigger in an indicator that a risk event could occur. Please help!  Which one is the correct answer? 


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

Weighting System vs Qualification Sellers list


--以下是內文--
Pre and Post Test on page 38 of Crosswind (厚):
70. A Project Manager is beginning the solicitation process to find companies that can potentially provide the needed services. The buyer wants to consider only sellers of the services that have met rigid predefined qualifications. What screening mechanism is this?
(A) Advertising
(B) Bidders conference
(C) Weighting System
(D) Qualification Sellers list
The answer of Crosswind is (D)
Can someone carifiy this? Why not weighting system?

(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

2008年10月30日 星期四

the Input of Communications Planing Process

The propose(output) the Communications Planing Process is to produce the Communications Management Plan...

So , Clearly , we may need the input as follow:
1. Enterprise environmental factors.
2. Organizational process assets.
3. Project management plan(Constraints adn Assumptions)
4. Project scope statement ??????
m............
But why should we need Project scope statement?

there are no clear relationship between Project scope statement and Communications Management plan


According the explanation on PMBOK P.226, it writes:
'The project scope statement (Section 5.2.3.1) provides a documented basis for
future project decisions and for confirming a common knowledge of project scope
among the stakeholders. Stakeholder analysis is completed as part of the Scope
Definition process.'

基本上,有看沒有懂,have any one a good explanation of that?


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

2008年10月22日 星期三

crosswind manual test of cost charpter

測驗的重點好像怪怪的,好像有些新版已不再提


特別是第10題
10. The highway project is in the middle of Planning when the project manager presents a status reporting method to the team. The team members haven't heard of this method before. It's called earned value. To attain buy-in from the team, the project manager begins to expain what earned value status reporting can do for the project, explaining that it will measure which of the following?

(A) time and cost
(B) scope, time and cost
(C) scope and cost
(D) scope and time

answer is (B) (Why not (A), why earned value is related scope?)
crosswind explain AC shows cost, PV shows time, EV shows scope.
^^^^^^^^^^^^?


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

2008年10月20日 星期一

Closing the project and contract closure

--此處輸入引言--


From crosswind manual test of chapter 6
25.
You network upgrade project is almost complete. You have outsourced the remote upgrades to three different companies for completion. As the project closes down, what comes first?

(A) Contract Closure
(B) Assignment of contracts for the next phase
(C) Release of resources
(D) Closing the project

The answer is (D). (Why not (A))

According to Crosswind opinion, closing the project happens before contract closure. But I don't find this relationship between these two process. Does it correct? How to explain?


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

2008年10月18日 星期六

博鴻 50th 第一組讀書會 10/24

起改地點如下:

時間:19:00 on 10/24, Friday

新地點:伯朗咖啡館南京二店
地址:台北市南京東路2段1號
電話:(02)2562-1633
到博鴻上課教室後,繼續往林森一直走到新生高架路口
Map is attached.







好處:據說有電源可使用notebook(等人時間繼續加班)
消費金額應該比春水堂低(一杯春水堂兩杯伯朗?)

進度:現場直接討論Crosswind薄本的Quality + Human Resources兩章的題目共60題。
(若還有時間可以再加上討論Rita的Quality + Human Resources兩章的題目。)
請盡量先在家把題目做過。
地圖:
http://maps.google.com/maps?q=%E5%8F%B0%E5%8C%97%E5%B8%82%E5%8D%97%E4%BA%AC%E6%9D%B1%E8%B7%AF2%E6%AE%B51%E8%99%9F&hl=zh-TW

Google Cal.
http://www.google.com/calendar/event?eid=NmZmNGEyb2IzNTA2NzZlM3RoczEwMTZzbW8gYWQ1Y2puNGZzMGwzbjhsZG5yZGpuMnJmdHNAZw&ctz=Asia/Taipei

行程總表:
http://docs.google.com/Doc?id=dcng88z_84gh5gk3hc

(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)
 