Residual Risk vs Secondary Risk

--此處輸入引言--


--以下是內文--
No. 110 on page 56 of Crosswind (厚):
The team implemnted a risk response plan when a vendor was unable to fulfill a contract commitment. The response was to choose another vendor. However, in this industry, it's hard to find a good company, and the one selected isn't that much better. The new company is somewhat better at meeting the terms of the contract, but still has some issue from time to time. What best describes these issues?
(A) Secondary risk
(B) Workaround
(C) Residual risk
(D) Risk respose plan
The answer of Crosswind (厚) is (C)
Why not (A) Secondary risk?

The definition of secondary risk means that risks result from the execution of a risk response. Right?  Can someone clarify this?
 

(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

A trigger is an indicator that a risk even will or could occur

--此處輸入引言--


--以下是內文--
183. All of the following are correct regarding risk triggers except...
(A) A trigger does not mean a risk will occur
(B) A trigger come before a risk
(C) A trigger in an indicator that a risk event could occur
(D) A trigger is an indicator that a risk even will occur 
The answer of Crosswind (厚) is (D)
I don't think that it's correct answer.
Refer to No. 26 of Crosswind (薄) on page 111, the anwser is  A trigger in an indicator that a risk event could occur. Please help!  Which one is the correct answer? 


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

Weighting System vs Qualification Sellers list


--以下是內文--
Pre and Post Test on page 38 of Crosswind (厚):
70. A Project Manager is beginning the solicitation process to find companies that can potentially provide the needed services. The buyer wants to consider only sellers of the services that have met rigid predefined qualifications. What screening mechanism is this?
(A) Advertising
(B) Bidders conference
(C) Weighting System
(D) Qualification Sellers list
The answer of Crosswind is (D)
Can someone carifiy this? Why not weighting system?

(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

2008年10月30日 星期四

the Input of Communications Planing Process

The propose(output) the Communications Planing Process is to produce the Communications Management Plan...

So , Clearly , we may need the input as follow:
1. Enterprise environmental factors.
2. Organizational process assets.
3. Project management plan(Constraints adn Assumptions)
4. Project scope statement ??????
m............
But why should we need Project scope statement?

there are no clear relationship between Project scope statement and Communications Management plan


According the explanation on PMBOK P.226, it writes:
'The project scope statement (Section 5.2.3.1) provides a documented basis for
future project decisions and for confirming a common knowledge of project scope
among the stakeholders. Stakeholder analysis is completed as part of the Scope
Definition process.'

基本上,有看沒有懂,have any one a good explanation of that?


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

2008年10月22日 星期三

crosswind manual test of cost charpter

測驗的重點好像怪怪的,好像有些新版已不再提


特別是第10題
10. The highway project is in the middle of Planning when the project manager presents a status reporting method to the team. The team members haven't heard of this method before. It's called earned value. To attain buy-in from the team, the project manager begins to expain what earned value status reporting can do for the project, explaining that it will measure which of the following?

(A) time and cost
(B) scope, time and cost
(C) scope and cost
(D) scope and time

answer is (B) (Why not (A), why earned value is related scope?)
crosswind explain AC shows cost, PV shows time, EV shows scope.
^^^^^^^^^^^^?


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

2008年10月20日 星期一

Closing the project and contract closure

--此處輸入引言--


From crosswind manual test of chapter 6
25.
You network upgrade project is almost complete. You have outsourced the remote upgrades to three different companies for completion. As the project closes down, what comes first?

(A) Contract Closure
(B) Assignment of contracts for the next phase
(C) Release of resources
(D) Closing the project

The answer is (D). (Why not (A))

According to Crosswind opinion, closing the project happens before contract closure. But I don't find this relationship between these two process. Does it correct? How to explain?


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

2008年10月18日 星期六

博鴻 50th 第一組讀書會 10/24

起改地點如下:

時間:19:00 on 10/24, Friday

新地點:伯朗咖啡館南京二店
地址:台北市南京東路2段1號
電話:(02)2562-1633
到博鴻上課教室後,繼續往林森一直走到新生高架路口
Map is attached.







好處:據說有電源可使用notebook(等人時間繼續加班)
消費金額應該比春水堂低(一杯春水堂兩杯伯朗?)

進度:現場直接討論Crosswind薄本的Quality + Human Resources兩章的題目共60題。
(若還有時間可以再加上討論Rita的Quality + Human Resources兩章的題目。)
請盡量先在家把題目做過。
地圖:
http://maps.google.com/maps?q=%E5%8F%B0%E5%8C%97%E5%B8%82%E5%8D%97%E4%BA%AC%E6%9D%B1%E8%B7%AF2%E6%AE%B51%E8%99%9F&hl=zh-TW

Google Cal.
http://www.google.com/calendar/event?eid=NmZmNGEyb2IzNTA2NzZlM3RoczEwMTZzbW8gYWQ1Y2puNGZzMGwzbjhsZG5yZGpuMnJmdHNAZw&ctz=Asia/Taipei

行程總表:
http://docs.google.com/Doc?id=dcng88z_84gh5gk3hc

(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

2008年10月17日 星期五

Who sign the Charter?

I think that the PM needs to get the approval and signature from his/her CEO before delivering any contract/service agreement to customer/sponsor for the approval and signature.
The key words of the question are "you are leaving your office", but you are still in your own office (not outside of your office) and "who will you go see for the signature" (also for the approval). Comparing Project Management Team, all Project Stakeholders and project sponsor with CEO of your company, I do think that CEO of your company is the best answer although PM would review the charter with project management team/senior management in his/her company. 
Please correct my answer if required.
----
This the question from PM PrepCastTM


You are the project manager for the Silver project. You have been brought on to this project in thYou he very early stages and you have been asked to write the charter for it. Over the past 10 days you have met with a number of stakeholders, received their input and you are now ready to have the charter signed. ave the charter in your hand and you are leaving your office. Who will you go see for the signature?

A.) Project Sponsor
B.) The Chief Executive Officer of your company
C.) All Project Stakeholders
D.) The Project Management Team





The answer is B.)

這一題,以我以前的關念,我會選 A) (找 CEO 有一點太大了吧?)
下面是出題者的說明……
不知道大家認不認同他的想法?
A project charter is normally signed by an authorized approver who is outside of the boundaries of the project. This ensures that authorization and funding is given from without and not from within the project. The Project Sponsor, Stakeholders and the Project Management Team are inside the boundaries of the project. While it may not be normal that the CEO signs a charter, in this question here, the CEO is the only person who is outside of the project boundaries and therefore the right person to sign it.


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

Chart of Accounts

This is the problem from crosswind....

The project planning is progressing. But the team has become frustrated working with the accounting department to set up a system of codes that the accounting department will use to track work on the project. This is known as what?
(A) Accounting codes.
(B) WBS numbering.
(C) Costbdgeting.
(D) Chart of accounts.





The answer is (D)
My question is Why not (A)?


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

2008年10月15日 星期三

Dependencies 的題目

Crosswind Custom Websites is building an ecommerce system. However, conflicting priorities from other projects has delayed the finish by two weeks. The schedule shows that the next task is to define the requirements needed by the customer, then that is followed by the coding. This is a example of what?

(A) Lag
(B) Crashing
(C) Discretionary Dependencies
(D) Mandatory Dependencies




Ans: D

請問大家對這一題的解伺釋為?

(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)




……(閱讀全文與回應)

2008年10月11日 星期六

One Question from Crosswind Exam Simulation Booklet

About Work Authorization System, We didn't see any descriptions in PMBOK.
Can anyone know why choose (C) answer in N0.11 of page 14 of Crosswind Exam Simulation Booklet






The team has been having issues with work being done as intented because of scope misinterpretation. They are consideringusing a Work Authorization System. What is the main propose of utilizing a Work Authorization System

(A) To show who is reponsible for what work
(B) To serve as a time tracking system
(C) To control Glod Plating
(D) To show what work is to be done in the project



(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)
……(閱讀全文與回應)

2008年10月8日 星期三

specification = scope statement ?



hello,
I have a question. In electrical industry, there is a important document, product specification.
Does specification equal to the scpoe statement? or just part of it?



(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

2008年10月5日 星期日

CPI 的考題……

這一題的答案,我是用估出來的,我不知道有沒有方式可以很精準的算出那一個答案……
有的話,麻煩分享你的算法……

You are project manager working on a construction project to build a bridge. You have completed half of the planned objective. The total planned cost at this stage is $500. The actual physical work that has been completed at this stage is worth $400. You have already spent $1000 on the project . what is the CPI?
A. 1.0
B. 0.5
C. 4.0
D. 0.4





The answer of this question is D

(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

Where could we find the risk list?

在http://www.free-pm-exam-questions.com/
讀到一題,滿有意思的……
跟大家分享……

You have recently joined as the project manager of a project. One of the project documents available to you lists all the risks in a hierarchical fashion. What is this document called?
A. Influence diagram.
B. Risk breakdown structure.
C. Risk management plan.
D. Risk register.

答案是什麼?先想想看再看答案哦……
按下下面「(閱讀全文並檢視所有回應)」,
就可以看答案了……
^__^





這一題有點陷阱
答案是 B....
想想看,為什麼 C 跟 D 兩個答案不對?

Immanuel,
Duncan


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

Are you ready to pay for your PMI membership fee and PMP Exam Fee recently?

2008年5月最新國外信用卡消費手續費率 - 2008-05-09, 10:25


Are you ready to pay for PMI membership fee and PMP Exam Fee recently? 













I found that some differences about handling fee of credit card, you can refer to the table below and hope it could be useful for your cost saving while you are going to use your credit card for paying your PMI membership fee and PMP Fee:
Bank   VISA Card    Master Card 
__________________________
永豐信用卡    1%     1%  
花旗銀行     2.20%      2.20% 
匯豐銀行     2.05%      2.05%  
荷蘭銀行     2.00%      2.00% 
中國信託     2.05%          2.05%  
台新銀行   1.55%    1.55% 
國泰世華銀行 1.55%    1.55% 
台北富邦銀行 1.55%    1.55%

--此處輸入引言--


--以下是內文--


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文與回應)

2008年10月2日 星期四

請問大家怎麼理解" Quality Control Measurements"?

"Quality Control Measurements" is the output of Perform Quality Control process
and
the input of Perform Quality Assurance process........



是指說……
Perform Quality Assurance process 中會有一堆的 QA 的行為(activity)....
and then 這一些 activity 的 Quality 也要有一些驗証的標準……
Quality Control Measurements 就是來驗証 QA activity 的標準……
如此我們可以說「 Quality Control Measurements 其實是 QA activity baseline」?
不知道這樣子解釋對不對?還請高手指點迷經……

Duncan