Dependencies 的題目

Crosswind Custom Websites is building an ecommerce system. However, conflicting priorities from other projects has delayed the finish by two weeks. The schedule shows that the next task is to define the requirements needed by the customer, then that is followed by the coding. This is a example of what?

(A) Lag
(B) Crashing
(C) Discretionary Dependencies
(D) Mandatory Dependencies




Ans: D

請問大家對這一題的解伺釋為?

(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)



3 則留言:

  1. 答案是D倒還能了解,只是一時想不到有甚麼Discretionary Dependency的例子.

    回覆刪除
  2. Dear Derick:

    m.....
    I feel so strange....
    '....conflicting priorities from other projects has delayed the finish by two weeks.....' should be the example of "External Dependencies"
    Why we only have the answer of "Mandatory Dependencies" ....
    Have you any idea?

    Duncan

    回覆刪除
  3. 我認為題目的第一段"..., conflicting priorities from other projects has delayed the finish by two weeks. "是煙霧,障眼法,和第二段"The schedule shows that the next task is to define the requirements needed by the customer, then that is followed by the coding. This is a example of what?" 無關。而define requireemnts 和coding是專案工作上的順序,屬於硬邏輯(hard logic),根據PMBOK定義,應該是Mandatory dependency.-- 以上是我的想法。

    回覆刪除

 