Which parts of the risk management process do not generally use organizational process assets as an input?
A Risk identification and qualitative risk analysis
B Qualitative and quantitative risk analysis
C Quantitative risk analysis and risk response planning
D Risk response planning and risk monitoring and control .
ANS:D
Since risk response planning focuses on previously identified risks and risk monitoring and control measures project performance, they do not need to make use of organizational process assets.
Source: PMBOKR Guide
通常在了解 ITTO 時,我不會特別花力氣思考在
Organizational process assets 以及 Eterprise Environmental Factors
這兩個 Input
只不過,這一題提醒了我,相關的東西還是思考一下
(謝謝 William 同學分享)
(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)
2008年11月30日 星期日
訂閱:
張貼留言 (Atom)
沒有留言:
張貼留言