Which parts of the risk management process do not generally use organizational process assets as an input?

A Risk identification and qualitative risk analysis

B Qualitative and quantitative risk analysis

C Quantitative risk analysis and risk response planning

D Risk response planning and risk monitoring and control .


ANS:D

Since risk response planning focuses on previously identified risks and risk monitoring and control measures project performance, they do not need to make use of organizational process assets.

Source: PMBOKR Guide