首頁 PMP證照後進修 PMP考試園地 書籍推薦 專案管理知識平台 志工專區

2008年11月28日 星期五

What is the MOST likely cause of poor risk management?

值得思考的題問……
我跟 william 同學有相同的問題……why?

Which of the following is the MOST likely cause of poor risk management?
A Inadequate risk response planning
B Poor risk monitoring and control
C Lack of a prioritized list of risks
D Lack of detail in the project scope statement



C
Risk management cannot proceed without a prioritized list of risks.

Can someone clarify this? Why prioritized list of risks? Why not Inadequate risk response planning?



(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

1 則留言:

  1. I'm sure. Just for discussion. I think you don't execute qualitative analysis if you lack of a prioritized list of risks. So you may not understand the impact of risk of your project. It causes bigger problems than that you do inadequate risk response planning.

    回覆刪除

 