28. Your new project to outsource work has been going badly. The project deliverables have changed three times, the functional managers keep removing people from the team and the project schedule baseline has been adjusted four times in the first week. This is MOST likely due to a lack of:
A a staffing management plan.
B a signed project charter.
C clear direction from the sponsor.
D a project scope management plan.
C
Although there are elements of poor scope management and project charter, the best choice is C.