Crosswind Custom Websites is building an ecommerce system. However, conflicting priorities from other projects has delayed the finish by two weeks. The schedule shows that the next task is to define the requirements needed by the customer, then that is followed by the coding. This is a example of what?
(A) Lag
(B) Crashing
(C) Discretionary Dependencies
(D) Mandatory Dependencies
Ans: D
請問大家對這一題的解伺釋為?
(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)
……(閱讀全文與回應)
2008年10月15日 星期三
2008年10月11日 星期六
One Question from Crosswind Exam Simulation Booklet
About Work Authorization System, We didn't see any descriptions in PMBOK.
Can anyone know why choose (C) answer in N0.11 of page 14 of Crosswind Exam Simulation Booklet
The team has been having issues with work being done as intented because of scope misinterpretation. They are consideringusing a Work Authorization System. What is the main propose of utilizing a Work Authorization System
(A) To show who is reponsible for what work
(B) To serve as a time tracking system
(C) To control Glod Plating
(D) To show what work is to be done in the project
(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)
……(閱讀全文與回應)
Can anyone know why choose (C) answer in N0.11 of page 14 of Crosswind Exam Simulation Booklet
The team has been having issues with work being done as intented because of scope misinterpretation. They are consideringusing a Work Authorization System. What is the main propose of utilizing a Work Authorization System
(A) To show who is reponsible for what work
(B) To serve as a time tracking system
(C) To control Glod Plating
(D) To show what work is to be done in the project
(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)
……(閱讀全文與回應)
2008年10月8日 星期三
specification = scope statement ?
hello,
I have a question. In electrical industry, there is a important document, product specification.
Does specification equal to the scpoe statement? or just part of it?
(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)
……(閱讀全文與回應)
2008年10月5日 星期日
CPI 的考題……
這一題的答案,我是用估出來的,我不知道有沒有方式可以很精準的算出那一個答案……
有的話,麻煩分享你的算法……
You are project manager working on a construction project to build a bridge. You have completed half of the planned objective. The total planned cost at this stage is $500. The actual physical work that has been completed at this stage is worth $400. You have already spent $1000 on the project . what is the CPI?
A. 1.0
B. 0.5
C. 4.0
D. 0.4
The answer of this question is D
(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)
……(閱讀全文與回應)
有的話,麻煩分享你的算法……
You are project manager working on a construction project to build a bridge. You have completed half of the planned objective. The total planned cost at this stage is $500. The actual physical work that has been completed at this stage is worth $400. You have already spent $1000 on the project . what is the CPI?
A. 1.0
B. 0.5
C. 4.0
D. 0.4
The answer of this question is D
(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)
……(閱讀全文與回應)
Where could we find the risk list?
在http://www.free-pm-exam-questions.com/
讀到一題,滿有意思的……
跟大家分享……
You have recently joined as the project manager of a project. One of the project documents available to you lists all the risks in a hierarchical fashion. What is this document called?
A. Influence diagram.
B. Risk breakdown structure.
C. Risk management plan.
D. Risk register.
答案是什麼?先想想看再看答案哦……
按下下面「(閱讀全文並檢視所有回應)」,
就可以看答案了……
^__^
這一題有點陷阱
答案是 B....
想想看,為什麼 C 跟 D 兩個答案不對?
Immanuel,
Duncan
(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)
……(閱讀全文與回應)
讀到一題,滿有意思的……
跟大家分享……
You have recently joined as the project manager of a project. One of the project documents available to you lists all the risks in a hierarchical fashion. What is this document called?
A. Influence diagram.
B. Risk breakdown structure.
C. Risk management plan.
D. Risk register.
答案是什麼?先想想看再看答案哦……
按下下面「(閱讀全文並檢視所有回應)」,
就可以看答案了……
^__^
這一題有點陷阱
答案是 B....
想想看,為什麼 C 跟 D 兩個答案不對?
Immanuel,
Duncan
(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)
……(閱讀全文與回應)
Are you ready to pay for your PMI membership fee and PMP Exam Fee recently?
2008年5月最新國外信用卡消費手續費率 - 2008-05-09, 10:25
Are you ready to pay for PMI membership fee and PMP Exam Fee recently?
I found that some differences about handling fee of credit card, you can refer to the table below and hope it could be useful for your cost saving while you are going to use your credit card for paying your PMI membership fee and PMP Fee:
Bank VISA Card Master Card
__________________________
永豐信用卡 1% 1%
永豐信用卡 1% 1%
花旗銀行 2.20% 2.20%
匯豐銀行 2.05% 2.05%
荷蘭銀行 2.00% 2.00%
中國信託 2.05% 2.05%
台新銀行 1.55% 1.55%
國泰世華銀行 1.55% 1.55%
台北富邦銀行 1.55% 1.55%匯豐銀行 2.05% 2.05%
荷蘭銀行 2.00% 2.00%
中國信託 2.05% 2.05%
台新銀行 1.55% 1.55%
國泰世華銀行 1.55% 1.55%
……(閱讀全文與回應)
2008年10月2日 星期四
請問大家怎麼理解" Quality Control Measurements"?
"Quality Control Measurements" is the output of Perform Quality Control process
and
the input of Perform Quality Assurance process........
是指說……Perform Quality Assurance process 中會有一堆的 QA 的行為(activity)....
and then 這一些 activity 的 Quality 也要有一些驗証的標準……
而 Quality Control Measurements 就是來驗証 QA activity 的標準……
如此我們可以說「 Quality Control Measurements 其實是 QA activity baseline」?
不知道這樣子解釋對不對?還請高手指點迷經……
Duncan
(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)
……(閱讀全文與回應)
and
the input of Perform Quality Assurance process........
是指說……Perform Quality Assurance process 中會有一堆的 QA 的行為(activity)....
and then 這一些 activity 的 Quality 也要有一些驗証的標準……
而 Quality Control Measurements 就是來驗証 QA activity 的標準……
如此我們可以說「 Quality Control Measurements 其實是 QA activity baseline」?
不知道這樣子解釋對不對?還請高手指點迷經……
Duncan
(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)
……(閱讀全文與回應)
訂閱:
文章 (Atom)